Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-107-05-50 06-419614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-41-R30.4/R31.8 Federal Project: NONE Progress payment No. 24 Payment period ending: 10-16-08 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 02305 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,566,571.64 0.00 2.a. Extra Work 304,876.76 3,661.81 b. Adjustment Comp. -51,617.32 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,819,831.08 3,661.81 5. Mobilization 518,000.00 0.00 6. Total Work Completed 5,337,831.08 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -238,906.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 238,906.51 0.00 9. Total pay to Contractor 5,327,831.08 3,661.81 10. Reduction Amt to Escrow -238,900.00 0.00 11. Payment to Escrow 238,900.00 12. Net Pymt. this Estimate 3,661.81