Dept. of Trans. FINAL Serial No. Contract No. 09-117-06-02 06-419614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-41-R30.4/R31.8 Federal Project: NONE Progress payment No. 25 Payment period ending: 10-16-08 SHASTA CONSTRUCTORS INC P O BOX 491539 REDDING CA 960491539 Escrow No. 02305 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,566,571.64 0.00 2.a. Extra Work 310,830.67 5,953.91 b. Adjustment Comp. -51,617.32 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,825,784.99 5,953.91 5. Mobilization 518,000.00 0.00 6. Total Work Completed 5,343,784.99 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -238,906.51 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 238,906.51 0.00 9. Total pay to Contractor 5,333,784.99 5,953.91 10. Reduction Amt to Escrow -238,900.00 0.00 11. Payment to Escrow 238,900.00 12. Net Pymt. this Estimate 5,953.91