Dept. of Trans. PROGRESS Serial No. Contract No. 11-053-08-48 06-426304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP UNSAT 06-KER-184-8.4/8.8 Federal Project: ACHS-P184(12) STPG-P184(12) Progress payment No. 12 Payment period ending: 02-20-11 GRIFFITH COMPANY 1128 CARRIER PARKWAY AVENUE BAKERSFIELD CA 93308 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 697,002.76 0.00 2.a. Extra Work 42,326.59 12,959.28 b. Adjustment Comp. 3,420.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 742,749.35 12,959.28 5. Mobilization 82,423.00 0.00 6. Total Work Completed 825,172.35 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. -1,295.93 -1,295.93 c. Reduction after 95% Comp. 9. Total pay to Contractor 823,876.42 21,663.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,663.35