Dept. of Trans. FINAL Serial No. Contract No. 08-184-08-50 06-430504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KIN-33-0.0/7.8 Federal Project: ACST-S033(65) P-S033(65) Progress payment No. 12 Payment period ending: 04-01-08 TEICHERT CONSTRUCTION P O BOX 400 KINGSBURG CA 93631 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,842,241.98 -9,429.30 2.a. Extra Work 159,247.62 0.00 b. Adjustment Comp. 333,749.37 2,373.50 3. Materials on Hand 4. Earned Subject to Retention 6,335,238.97 -7,055.80 5. Mobilization 340,380.00 0.00 6. Total Work Completed 6,675,618.97 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,675,618.97 2,944.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,944.20