Dept. of Trans. PROGRESS Serial No. Contract No. 17-080-09-23 06-430714 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 32% Location: Federal Project: 06-TUL-216-1.9/2.9 NONE Progress payment No. 017 Payment period ending: 03-20-17 WABO LANDSCAPE & CONSTRUCTION INC 726 ALFRED NOBEL DR HERCULES CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 233,211.60 0.00 2. a. Extra Work 35,562.95 3,913.76 b. Adustment Comp. 946.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 269,720.55 3,913.76 5. Mobilization 30,600.00 0.00 6. Total Work Completed 300,320.55 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 290,320.55 3,913.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,913.76