Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-155-07-30 06-432004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-TUL-99-51.9/ .0 Federal Project: ACST-P099(497) PHG-P099(497) Progress payment No. 17 Payment period ending: 05-05-09 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,682,516.15 0.00 2.a. Extra Work 158,316.42 5,639.36 b. Adjustment Comp. -20,680.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,820,152.57 5,639.36 5. Mobilization 6. Total Work Completed 2,820,152.57 7. Deductions -12,312.60 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,807,839.97 5,639.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,639.36