Dept. of Trans. PROGRESS Serial No. Contract No. 15-168-14-34 06-432604 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 10% Location: Federal Project: 06-FRE-33-10.9/11.1 STP-P033(79) Progress payment No. 002 Payment period ending: 06-20-15 MYERS AND SONS CONSTRUCTION, LP 4600 NORTHGATE BLVD SUITE 100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 382,389.34 293,740.81 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 382,389.34 293,740.81 5. Mobilization 266,250.00 266,250.00 6. Total Work Completed 648,639.34 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 648,639.34 559,990.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 559,990.81