Dept. of Trans. PROGRESS Serial No. Contract No. 19-233-11-11 06-442544 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 68% Location: Federal Project: 06-KER-46-30.5/33.5 PLUL-6206(21) Progress payment No. 019 Payment period ending: 08-20-19 SECURITY PAVING COMPANY INC 13170 TELFAIR AVE SYLMAR CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,195,731.85 869,905.04 2. a. Extra Work 581,533.19 0.00 b. Adustment Comp. 151,644.67 0.00 3. Materials on Hand 179,546.37 -528.14 4. Earned Subject to Retention 15,108,456.08 869,376.90 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 16,328,909.71 7. Deductions -332,362.85 -272,362.85 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,176,093.23 597,014.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 597,014.05