Dept. of Trans. PROGRESS Serial No. Contract No. 19-354-10-58 06-442544 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 84% Location: Federal Project: 06-KER-46-30.5/33.5 PLUL-6206(21) Progress payment No. 023 Payment period ending: 12-20-19 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,960,727.94 1,192,191.19 2. a. Extra Work 709,072.84 52,322.14 b. Adustment Comp. 125,603.31 -26,041.36 3. Materials on Hand 167,803.11 14,501.97 4. Earned Subject to Retention 18,963,207.20 1,232,973.94 5. Mobilization 1,400,000.00 0.00 6. Total Work Completed 20,195,404.09 7. Deductions -570,599.18 -316,872.80 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,792,608.02 916,101.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 916,101.14