Dept. of Trans. PROGRESS Serial No. Contract No. 22-327-12-21 06-442554 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 48% Location: Federal Project: 06-KER-46-29.7/31.9 PLUL-6206(31) Progress payment No. 019 Payment period ending: 11-20-22 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,400,844.06 374,181.00 2. a. Extra Work 761,654.34 0.00 b. Adustment Comp. 578,481.70 0.00 3. Materials on Hand 142,273.00 142,273.00 4. Earned Subject to Retention 12,883,253.10 516,454.00 5. Mobilization 750,000.00 0.00 6. Total Work Completed 13,490,980.10 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,623,253.10 516,454.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 516,454.00