Dept. of Trans. PROGRESS Serial No. Contract No. 24-170-14-43 06-442564 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 63% Location: Federal Project: 06-KER-46-26.1/30.2 PLUL-6206(31) Progress payment No. 009 Payment period ending: 06-20-24 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,092,675.41 3,801,490.50 2. a. Extra Work 195,682.95 167,995.23 b. Adustment Comp. 134,305.16 -35,077.57 3. Materials on Hand 4. Earned Subject to Retention 16,422,663.52 3,934,408.16 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 18,222,663.52 7. Deductions -20,000.00 20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,202,663.52 3,954,408.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,954,408.16