Dept. of Trans. PROGRESS Serial No. Contract No. 25-021-14-16 06-442564 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 81% Location: Federal Project: 06-KER-46-26.1/30.2 PLUL-6206(31) Progress payment No. 014 Payment period ending: 01-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,960,620.27 2,900.00 2. a. Extra Work 368,623.51 47,743.99 b. Adustment Comp. 143,052.52 -48,703.87 3. Materials on Hand 4. Earned Subject to Retention 22,472,296.30 1,940.12 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 24,272,296.30 7. Deductions -10,000.00 58,703.87 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 24,262,296.30 60,643.99 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 60,643.99