Dept. of Trans. PROGRESS Serial No. Contract No. 10-354-12-31 06-442614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 3% 12% 06-FRE-99-26.7/30.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 12-20-10 DE SILVA GATES CONSTRUCTION P O BOX 2909 DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 469,557.75 175,809.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 0.00 -60,450.00 4. Earned Subject to Retention 469,557.75 115,359.00 5. Mobilization 6. Total Work Completed 469,557.75 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 469,557.75 115,359.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 115,359.00