Dept. of Trans. PROGRESS Serial No. Contract No. 13-169-15-58 06-442624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 9% 06-FRE-99-26.7/R31.6 Federal Project: 06-MAD-99-R0.0/R1.6 NONE Progress payment No. 07 Payment period ending: 06-20-13 MCM CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,876,153.88 1,786,388.93 2.a. Extra Work 262,635.29 141,576.94 b. Adjustment Comp. 3. Materials on Hand 1,895,769.24 -84,195.18 4. Earned Subject to Retention 9,034,558.41 1,843,770.69 5. Mobilization 3,782,049.75 796,221.00 6. Total Work Completed 10,920,838.92 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 12,806,608.16 2,639,991.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,639,991.69