Dept. of Trans. PROGRESS Serial No. Contract No. 13-266-07-41 06-442624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 16% 06-FRE-99-26.7/R31.6 Federal Project: 06-MAD-99-R0.0/R1.6 NONE Progress payment No. 10 Payment period ending: 09-20-13 MCM CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,325,478.56 1,052,052.78 2.a. Extra Work 447,122.51 27,291.02 b. Adjustment Comp. 67,437.04 -1,703.42 3. Materials on Hand 1,407,118.90 -228,398.89 4. Earned Subject to Retention 12,247,157.01 849,241.49 5. Mobilization 3,782,049.75 0.00 6. Total Work Completed 14,622,087.86 7. Deductions -20,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 16,009,206.76 849,241.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 849,241.49