Dept. of Trans. PROGRESS Serial No. Contract No. 14-169-14-37 06-442624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 38% 06-FRE-99-26.7/R31.6 Federal Project: 06-MAD-99-R0.0/R1.6 NONE Progress payment No. 19 Payment period ending: 06-20-14 MCM CONSTRUCTION INC P O BOX 620 NORTH HIGHLANDS CA 956600620 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,749,314.68 2,369,482.69 2.a. Extra Work 850,545.54 154,602.93 b. Adjustment Comp. 263,435.45 31,986.35 3. Materials on Hand 660,258.27 -415,458.07 4. Earned Subject to Retention 26,523,553.94 2,140,613.90 5. Mobilization 3,981,105.00 0.00 6. Total Work Completed 29,844,400.67 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 30,499,658.94 2,140,613.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,140,613.90