Dept. of Trans. PROGRESS Serial No. Contract No. 10-235-08-16 06-447704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 18% 06-FRE-41-R29.8/R30.4 Federal Project: NH-P041(114) Progress payment No. 02 Payment period ending: 08-20-10 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 306,701.03 180,885.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 747.19 747.19 4. Earned Subject to Retention 307,448.22 181,632.19 5. Mobilization 162,500.00 162,500.00 6. Total Work Completed 469,201.03 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 469,948.22 344,132.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 344,132.19