Dept. of Trans. PROGRESS Serial No. Contract No. 07-268-05-53 06-451604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 69% 06-KER-99-24.7/27.1 Federal Project: ACNH-P099(479) Progress payment No. 12 Payment period ending: 09-20-07 A C C U CONSTRUCTION 23135 BETTY ROAD PERRIS CA 92570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,856,890.50 227,451.50 2.a. Extra Work 28,666.73 4,783.99 b. Adjustment Comp. 53,969.26 43,456.60 3. Materials on Hand 4. Earned Subject to Retention 1,939,526.49 275,692.09 5. Mobilization 206,000.00 0.00 6. Total Work Completed 2,145,526.49 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,145,526.49 275,692.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 275,692.09