Dept. of Trans. PROGRESS Serial No. Contract No. 04-237-06-49 06-455504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 6% 06-TUL-99-40.4/ .0 Federal Project: ACST-P099(461) PE-P099(461) STPL-5946(46) Progress payment No. 01 Payment period ending: 08-20-04 AGEE CONSTRUCTION CORPORATION P O BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 139,335.40 139,335.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 139,335.40 139,335.40 5. Mobilization 130,000.00 130,000.00 6. Total Work Completed 269,335.40 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 269,335.40 269,335.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 269,335.40