Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-273-12-20 06-458604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-99-12.2/14.5 Federal Project: ACST-P099(482) PE-P099(482) STPL-6206(5) Progress payment No. 32 Payment period ending: 09-24-09 J S BRAR COMPANY INC 2779 BULLARD AVE CLOVIS CA 93611 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 438,422.36 1,478.40 2.a. Extra Work 19,004.18 2,562.94 b. Adjustment Comp. 11,136.75 0.00 3. Materials on Hand 4. Earned Subject to Retention 468,563.29 4,041.34 5. Mobilization 2,400.00 0.00 6. Total Work Completed 470,963.29 7. Deductions -21,000.00 -21,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 449,963.29 -16,958.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -16,958.66