Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-306-06-46 06-458704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-FRE-99-7.3/11.1 Federal Project: NH-P099(535) Progress payment No. 08 Payment period ending: 09-29-11 TEICHERT CONSTRUCTION P O BOX 520 FOWLER CA 936250520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,864,594.03 68,070.00 2.a. Extra Work 50,443.73 41,327.34 b. Adjustment Comp. 135,012.06 16,239.07 3. Materials on Hand 4. Earned Subject to Retention 3,050,049.82 125,636.41 5. Mobilization 216,000.00 0.00 6. Total Work Completed 3,266,049.82 7. Deductions 0.00 9,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,266,049.82 134,636.41 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 134,636.41