Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-136-09-36 06-460204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-223-20.1/21.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 04-23-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,208,448.76 -5,899.50 2.a. Extra Work 4,838.57 4,838.57 b. Adjustment Comp. 48,429.43 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,261,716.76 -1,060.93 5. Mobilization 6. Total Work Completed 1,261,716.76 7. Deductions -2,289.66 20,000.00 8. a.Contract Retentions -59,572.58 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 59,572.58 0.00 9. Total pay to Contractor 1,259,427.10 18,939.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 18,939.07