Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-05-18 06-460704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 100% 06-KER-5-0.0/10.2 Federal Project: ACIM-005-4(180) Progress payment No. 08 Payment period ending: 11-20-09 SECURITY PAVING COMPANY INC P O BOX 1489 SUN VALLEY CA 913531489 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,518,331.78 1,768,641.99 2.a. Extra Work 25,244.52 8,356.52 b. Adjustment Comp. -516,620.53 -517,235.74 3. Materials on Hand 4. Earned Subject to Retention 13,026,955.77 1,259,762.77 5. Mobilization 355,000.00 0.00 6. Total Work Completed 13,381,955.77 7. Deductions -1,249,300.00 -1,072,300.00 8. a.Contract Retentions b. Unsatisfactory Prog. 0.00 851,600.15 c. Reduction after 95% Comp. 9. Total pay to Contractor 12,132,655.77 1,039,062.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,039,062.92