Dept. of Trans. PROGRESS Serial No. Contract No. 18-201-10-55 06-461504 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 6% Location: Federal Project: 06-TUL-190-0.0/8.0 ACST-P190(22) Progress payment No. 001 Payment period ending: 07-20-18 YARBS GRADING & PAVING INC 11339 S PEACH AVE FRESNO CA 93725 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 673,154.90 673,154.90 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 673,154.90 673,154.90 5. Mobilization 253,325.00 253,325.00 6. Total Work Completed 926,479.90 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 926,479.90 926,479.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 926,479.90