Dept. of Trans. PROGRESS Serial No. Contract No. 19-141-11-35 06-461504 PROGRESS PAYMENT VOUCHER %complete: %time: 57% 61% Location: Federal Project: 06-TUL-190-0.0/8.0 ACST-P190(22) Progress payment No. 011 Payment period ending: 05-20-19 YARBS GRADING & PAVING INC PO BOX 87 FOWLER CA 93625 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 6,260,495.66 600,457.16 2. a. Extra Work 152,964.52 6,893.13 b. Adustment Comp. 232,111.01 0.00 3. Materials on Hand 0.00 -51,267.00 4. Earned Subject to Retention 6,645,571.19 556,083.29 5. Mobilization 506,650.00 0.00 6. Total Work Completed 7,152,221.19 7. Deductions -20,715.52 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 7,131,505.67 556,083.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 556,083.29