Dept. of Trans. PROGRESS Serial No. Contract No. 14-325-09-04 06-462204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 55% 50% 06-KIN-198-R14.8/17.9 Federal Project: ACNH-P198(60) Progress payment No. 12 Payment period ending: 11-20-14 GRANITE CONSTRUCTION COMPANY 2716 GRANITE COURT FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,392,199.66 0.00 2.a. Extra Work 921,705.29 247,749.71 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,313,904.95 247,749.71 5. Mobilization 440,000.00 22,000.00 6. Total Work Completed 2,753,904.95 7. Deductions -5,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,748,904.95 269,749.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 269,749.71