Dept. of Trans. PROGRESS Serial No. Contract No. 08-267-06-58 06-462804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 43% 20% 06-FRE-99-21.4/R22.4 Federal Project: 06-FRE-180-R56.5/R58.4 NONE Progress payment No. 04 Payment period ending: 09-20-08 WATKIN AND BORTOLUSSI INC 77 LARKSPUR STREET SAN RAFAEL CA 949014886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 576,639.50 161,672.30 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 130,000.00 130,000.00 4. Earned Subject to Retention 706,639.50 291,672.30 5. Mobilization 161,500.00 0.00 6. Total Work Completed 738,139.50 7. Deductions 8. a.Contract Retentions -35,331.98 -4,155.66 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 832,807.52 287,516.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 287,516.64