Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-07-17 06-462904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 98% 06-KER-5-54.1/ .0 Federal Project: ACHS-005-4(181) IMG-005-4(181) Progress payment No. 10 Payment period ending: 07-20-09 BOWE CONTRACTORS INC 42424 N 4TH STREET EAST LANCASTER CA 93535 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,246,435.76 277,915.04 2.a. Extra Work 96,549.66 27,170.33 b. Adjustment Comp. -5,600.00 -5,600.00 3. Materials on Hand 4. Earned Subject to Retention 2,337,385.42 299,485.37 5. Mobilization 6. Total Work Completed 2,337,385.42 7. Deductions -2,380.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,335,005.42 299,485.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 299,485.37