Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-07-56 06-463004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 76% 71% 06-KER-58-R139.0/ .0 Federal Project: ACHS-P058(105) NHG-P058(105) Progress payment No. 14 Payment period ending: 10-20-09 BOWE CONTRACTORS INC 42424 N 4TH STREET EAST LANCASTER CA 93535 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,858,643.80 280,458.60 2.a. Extra Work 64,093.80 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,922,737.60 280,458.60 5. Mobilization 6. Total Work Completed 4,922,737.60 7. Deductions -1,500.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,921,237.60 280,458.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 280,458.60