Dept. of Trans. PROGRESS Serial No. Contract No. 05-172-06-13 06-464804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 53% 06-KER-99-13.4/16.7 Federal Project: ACST-P099(490) PHG-P099(490) Progress payment No. 02 Payment period ending: 06-20-05 MODERN ALLOYS INC 11172 WESTERN AVENUE STANTON CA 90680 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 504,236.70 447,979.40 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 504,236.70 447,979.40 5. Mobilization 15,300.00 7,650.00 6. Total Work Completed 519,536.70 7. Deductions -225.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 519,311.70 455,629.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 455,629.40