Dept. of Trans. PROGRESS Serial No. Contract No. 20-084-09-05 06-470904 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 33% Location: Federal Project: 06-MAD-99-R7.5/15.1 B1NH-P099(635) Progress payment No. 008 Payment period ending: 03-20-20 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,685,029.16 1,528,732.60 2. a. Extra Work 322,573.60 -3,260.85 b. Adustment Comp. 176,319.83 176,319.83 3. Materials on Hand 1,197,554.06 76,206.74 4. Earned Subject to Retention 13,381,476.65 1,777,998.32 5. Mobilization 2,776,787.30 584,586.80 6. Total Work Completed 14,960,709.89 7. Deductions -50,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,108,263.95 2,352,585.12 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,352,585.12