Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 21-006-12-39 06-470904 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 70% Location: Federal Project: 06-MAD-99-R7.5/15.1 B1NH-P099(635) Progress payment No. 020 Payment period ending: 12-20-20 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 33,501,478.52 194,934.05 2. a. Extra Work 1,237,331.02 0.00 b. Adustment Comp. 111,689.93 0.00 3. Materials on Hand 544,483.79 411,604.00 4. Earned Subject to Retention 35,394,983.26 606,538.05 5. Mobilization 2,922,934.00 0.00 6. Total Work Completed 37,773,433.47 7. Deductions -54,150.00 422,794.02 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,263,767.26 1,029,332.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,029,332.07