Dept. of Trans. PROGRESS Serial No. Contract No. 21-053-08-34 06-470904 PROGRESS PAYMENT VOUCHER %complete: %time: 66% 80% Location: Federal Project: 06-MAD-99-R7.5/15.1 B1NH-P099(635) Progress payment No. 023 Payment period ending: 02-20-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,387,349.04 3,466,660.03 2. a. Extra Work 1,294,294.25 27,542.00 b. Adustment Comp. 111,689.93 0.00 3. Materials on Hand 529,350.43 -15,133.36 4. Earned Subject to Retention 42,322,683.65 3,479,068.67 5. Mobilization 2,922,934.00 0.00 6. Total Work Completed 44,716,267.22 7. Deductions -65,150.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 45,180,467.65 3,478,068.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,478,068.67