Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 21-067-10-26 06-470904 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 80% Location: Federal Project: 06-MAD-99-R7.5/15.1 B1NH-P099(635) Progress payment No. 024 Payment period ending: 02-20-21 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 40,661,652.49 274,303.45 2. a. Extra Work 1,294,294.25 0.00 b. Adustment Comp. 68,317.59 -43,372.34 3. Materials on Hand 529,350.43 0.00 4. Earned Subject to Retention 42,553,614.76 230,931.11 5. Mobilization 2,922,934.00 0.00 6. Total Work Completed 44,947,198.33 7. Deductions -65,150.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 45,411,398.76 230,931.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 230,931.11