Dept. of Trans. PROGRESS Serial No. Contract No. 14-084-08-17 06-471004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 36% 37% 06-MAD-99-R6.9/R8.2 Federal Project: NONE Progress payment No. 12 Payment period ending: 03-20-14 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SLYMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,927,299.44 1,356,583.84 2.a. Extra Work 61,825.47 16,734.03 b. Adjustment Comp. 27,576.53 0.00 3. Materials on Hand 4. Earned Subject to Retention 14,016,701.44 1,373,317.87 5. Mobilization 1,821,150.95 0.00 6. Total Work Completed 15,837,852.39 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 15,837,852.39 1,373,317.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,373,317.87