Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-10-10 06-471004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 56% 61% 06-MAD-99-R6.9/R8.2 Federal Project: NONE Progress payment No. 19 Payment period ending: 10-20-14 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SLYMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 22,678,452.31 1,165,603.45 2.a. Extra Work 344,088.21 182,894.89 b. Adjustment Comp. 32,636.53 0.00 3. Materials on Hand 212,240.00 0.00 4. Earned Subject to Retention 23,267,417.05 1,348,498.34 5. Mobilization 1,917,001.00 0.00 6. Total Work Completed 24,972,178.05 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 25,184,418.05 1,348,498.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,348,498.34