Dept. of Trans. PROGRESS Serial No. Contract No. 15-299-13-07 06-471004 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 98% Location: Federal Project: 06-MAD-99-R6.9/R8.2 NONE Progress payment No. 032 Payment period ending: 10-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SLYMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,247,000.51 590,579.58 2. a. Extra Work 804,970.95 13,923.99 b. Adustment Comp. 130,715.25 0.00 3. Materials on Hand 102,108.85 0.00 4. Earned Subject to Retention 35,284,795.56 604,503.57 5. Mobilization 1,917,001.00 0.00 6. Total Work Completed 37,099,687.71 7. Deductions -23,479.88 172,361.08 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 37,178,316.68 776,864.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 776,864.65