Dept. of Trans. PROGRESS Serial No. Contract No. 15-324-09-56 06-471004 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 100% Location: Federal Project: 06-MAD-99-R6.9/R8.2 NONE Progress payment No. 033 Payment period ending: 11-20-15 SECURITY PAVING COMPANY INC 13170 TELFAIR AVENUE SLYMAR, CA 91342 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,208,606.55 961,606.04 2. a. Extra Work 810,290.34 5,319.39 b. Adustment Comp. 130,715.25 0.00 3. Materials on Hand 66,516.35 -35,592.50 4. Earned Subject to Retention 36,216,128.49 931,332.93 5. Mobilization 1,917,001.00 0.00 6. Total Work Completed 38,066,613.14 7. Deductions -23,479.88 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 38,109,649.61 931,332.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 931,332.93