Dept. of Trans. PROGRESS Serial No. Contract No. 18-053-10-21 06-471504 PROGRESS PAYMENT VOUCHER %complete: %time: 61% 46% Location: Federal Project: 06-TUL-99-39.6/41.3 NONE Progress payment No. 010 Payment period ending: 02-20-18 GRANITE CONSTRUCTION COMPANY PO BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,495,885.13 1,782,475.05 2. a. Extra Work 276,167.72 53,677.64 b. Adustment Comp. 319,782.45 15,822.94 3. Materials on Hand 25,104.14 0.00 4. Earned Subject to Retention 16,116,939.44 1,851,975.63 5. Mobilization 3,116,000.00 155,800.00 6. Total Work Completed 19,207,835.30 7. Deductions -27,229.28 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 19,205,710.16 2,007,775.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,007,775.63