Dept. of Trans. PROGRESS Serial No. Contract No. 07-297-05-23 06-471604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 84% 06-TUL-198-R18.8/ .0 Federal Project: ACNH-P198(50) STPL-6206(8) H-6206(8) Progress payment No. 02 Payment period ending: 10-20-07 TEICHERT CONSTRUCTION P O BOX 400 KINGSBURG CA 93631 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 729,221.29 477,119.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 729,221.29 477,119.29 5. Mobilization 6. Total Work Completed 729,221.29 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -47,711.93 -47,711.93 c. Reduction after 95% Comp. 9. Total pay to Contractor 681,509.36 429,407.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 429,407.36