Dept. of Trans. PROGRESS Serial No. Contract No. 07-205-13-06 06-480204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 5% 9% 06-MAD-5702 Federal Project: NONE Progress payment No. 01 Payment period ending: 07-20-07 CRUCO CONSTRUCTION 2443 FOUNDRY PARK AVE FRESNO CA 93706 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,725.00 12,725.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 12,725.00 12,725.00 5. Mobilization 6. Total Work Completed 12,725.00 7. Deductions 8. a.Contract Retentions -1,272.50 -1,272.50 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 11,452.50 11,452.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,452.50