Dept. of Trans. PROGRESS Serial No. Contract No. 09-294-10-38 06-480504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 06-FRE-99-R1.0/ .0 Federal Project: 06-FRE-99-6.5/ .0 NONE 06-FRE-99-9.2/ .0 Progress payment No. 06 Payment period ending: 10-20-09 CLAYBORN CONTRACTING GROUP INC 10556 COMBIE ROAD PMB 6203 AUBURN CA 95602 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 421,778.91 74,401.60 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 60,556.67 60,556.67 4. Earned Subject to Retention 482,335.58 134,958.27 5. Mobilization 6. Total Work Completed 421,778.91 7. Deductions -1,350.00 0.00 8. a.Contract Retentions -24,116.78 -6,747.91 b. Unsatisfactory Prog. 0.00 11,553.53 c. Reduction after 95% Comp. 9. Total pay to Contractor 456,868.80 139,763.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 139,763.89