Dept. of Trans. PROGRESS Serial No. Contract No. 05-208-05-09 06-480804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 85% 06-KER-58-77.0/82.6 Federal Project: NONE Progress payment No. 04 Payment period ending: 07-20-05 MANHOLE ADJUSTING CONTRACTORS INC 9500 BEVERLY ROAD PICO RIVERA CA 906602135 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 478,622.06 1,360.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 478,622.06 1,360.00 5. Mobilization 64,000.00 0.00 6. Total Work Completed 542,622.06 7. Deductions 8. a.Contract Retentions -23,931.10 -68.00 b. Unsatisfactory Prog. 0.00 23,605.60 c. Reduction after 95% Comp. 9. Total pay to Contractor 518,690.96 24,897.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,897.60