Dept. of Trans. PROGRESS Serial No. Contract No. 11-207-07-05 06-483404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 86% 74% 06-KER-5722 Federal Project: NONE Progress payment No. 12 Payment period ending: 07-20-11 J T S CONSTRUCTION P O BOX 41765 BAKERSFIELD CA 93384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,882,085.92 181,829.84 2.a. Extra Work 69,865.03 33,582.52 b. Adjustment Comp. -1,234.17 -1,234.17 3. Materials on Hand 4. Earned Subject to Retention 2,950,716.78 214,178.19 5. Mobilization 6. Total Work Completed 2,950,716.78 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,950,716.78 214,178.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 214,178.19