Dept. of Trans. PROGRESS Serial No. Contract No. 11-236-09-16 06-483404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 81% 06-KER-5722 Federal Project: NONE Progress payment No. 13 Payment period ending: 08-20-11 J T S CONSTRUCTION P O BOX 41765 BAKERSFIELD CA 93384 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,170,471.43 288,385.51 2.a. Extra Work 69,865.03 0.00 b. Adjustment Comp. -1,234.17 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,239,102.29 288,385.51 5. Mobilization 6. Total Work Completed 3,239,102.29 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,234,102.29 283,385.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 283,385.51