Dept. of Trans. PROGRESS Serial No. Contract No. 25-297-08-17 06-487404 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 0% Location: Federal Project: 06-TUL-99-35.8/37.1 6206-039 Progress payment No. 004 Payment period ending: 10-20-25 GRANITE CONSTRUCTION COMPANY PO BOX 742478 LOS ANGELES CA 90074-2478 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 301,750.00 244,000.00 2. a. Extra Work 58,303.64 43,451.60 b. Adustment Comp. 3. Materials on Hand 393,540.00 393,540.00 4. Earned Subject to Retention 753,593.64 680,991.60 5. Mobilization 6. Total Work Completed 360,053.64 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 753,593.64 680,991.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 680,991.60