Dept. of Trans. PROGRESS Serial No. Contract No. 15-204-14-15 06-487504 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 57% Location: Federal Project: 06-KIN-198-R16.5/R17.2 NHP-P198(62) Progress payment No. 011 Payment period ending: 07-20-15 AGEE CONSTRUCTION CORPORATION PO BOX 629 CLOVIS CA 93613 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,597,949.91 633,429.26 2. a. Extra Work 34,725.06 8,217.58 b. Adustment Comp. 12,937.04 0.00 3. Materials on Hand 27,513.11 3,435.71 4. Earned Subject to Retention 4,673,125.12 645,082.55 5. Mobilization 130,000.00 6,500.00 6. Total Work Completed 4,775,612.01 7. Deductions -1,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,802,125.12 651,582.55 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 651,582.55