Dept. of Trans. SEMI-FINAL Serial No. Contract No. 05-178-13-09 06-493804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 06-KER-58-0.0/15.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-23-05 INTERMOUNTAIN SLURRY SEAL INC P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 694,706.35 0.00 2.a. Extra Work b. Adjustment Comp. -2,541.24 -2,541.24 3. Materials on Hand 4. Earned Subject to Retention 692,165.11 -2,541.24 5. Mobilization 6. Total Work Completed 692,165.11 7. Deductions 0.00 25,474.10 8. a.Contract Retentions -31,998.27 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 31,998.27 0.00 9. Total pay to Contractor 692,165.11 22,932.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 22,932.86