Dept. of Trans. PROGRESS Serial No. Contract No. 08-113-06-29 06-495504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 93% 06-KER-58-43.9/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 04-20-08 MAVERICK ASPHALT INC P O BOX 13490 BAKERSFIELD CA 93389 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 612,722.45 0.00 2.a. Extra Work 33,724.84 23,750.75 b. Adjustment Comp. 36,913.44 3,176.44 3. Materials on Hand 4. Earned Subject to Retention 683,360.73 26,927.19 5. Mobilization 18,284.00 0.00 6. Total Work Completed 701,644.73 7. Deductions 8. a.Contract Retentions -34,168.04 -1,346.36 b. Unsatisfactory Prog. -1,346.36 -1,346.36 c. Reduction after 95% Comp. 9. Total pay to Contractor 666,130.33 24,234.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,234.47