Dept. of Trans. PROGRESS Serial No. Contract No. 04-056-10-02 07-002304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 22% 07-LA-101-14.9/15.9 Federal Project: ACNH-Q101(41) Progress payment No. 03 Payment period ending: 02-20-04 PKB CONSTRUCTION INC P O BOX 661717 ARCADIA CA 91066 Escrow No. 02153 Total Estimate This Estimate 1. Contract Itms Without Mobil. 588,318.00 236,326.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 588,318.00 236,326.00 5. Mobilization 119,319.75 39,773.25 6. Total Work Completed 707,637.75 7. Deductions 0.00 10,000.00 8. a.Contract Retentions -58,831.80 -23,632.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 648,805.95 262,466.65 10. Reduction Amt to Escrow 11. Payment to Escrow 58,830.00 12. Net Pymt. this Estimate 262,466.65